Northstowe Unity Centre, Cambridgeshire
Northstowe's first ground source heat pump, designed and installed for Kier at the new town's community centre.

The brief
Kier was building the Unity Centre for South Cambridgeshire District Council: the community building at the heart of Northstowe, the new town north-west of Cambridge. The building needed low carbon heat from its own site.
What we did
Working for Kier, we designed and installed the ground source heat pump system that heats the building. Seven boreholes, each around 145 metres deep, sit beneath the centre's enclosed garden and draw steady heat from the ground.
We delivered the design, drilling, installation and commissioning as one package, so Kier had a single specialist responsible from the ground loop to the plant room.
The result
The Unity Centre opened in March 2026 with a main hall, café, offices, meeting rooms and a micro library, run by Northstowe Town Council. It is heated by Northstowe's first ground source heat pump.